Malczyce Hydropower Plant on the Oder River
Malczyce barrage consists of a 300m wide weir, 260 m long spillway, fish passage and a navigation lock – 190m long and 12m wide. The Project will include construction of a drainage system, drainage canal and pumping station.
Basic technical parameters of Hydropower Plant:
- installed discharge of 3 Kaplan turbines: 250 m3/s
- installed power capacity: 9.0 MW
- acceptable head range: 4.4 m ¸ 6.4 m
- average production: 48 900 MWh/year
Project
Malczyce Hydropower Plant on the Oder River
Investor
Government
Location
Malczyce
Time period
2011-2015