Weirs on the Oder River – phase I

PROJECT DESCRIPTION:

The main purpose of the modernization designed under this Contracts is to improve the very bad technical condition of the structures and their operating conditions, both during shipping and the dead (winter) seasons, as well as during the passage of flood waters.

TECHNICAL DATA:

  • OPATOWICE WEIR
    commissioned in 1985
    located at km 245.035 of the Oder River
    span 3 x 32.00 m = 96.00 m
    head 2.46 m
  • JANOWICE WEIR
    commissioned in 1990
    located at km 232.405 of the Oder River
    span 3 x 32.00 m = 96.00 m
    head 2.53 m
  • WROBLIN WEIR
    commissioned in 1976
    located at km 157.700 of the Oder River
    span 3 x 32.00 m = 96.00 m
    head 2.40 m
  • ZWANOWICE WEIR
    commissioned in 1976
    located at km 185.160 of the Oder River
    span 3 x 32.00 m = 96.00 m
    head 2.80 m
  • JANUSZKOWICE WEIR
    commissioned in 1977
    located at km 105.600 of the Oder River (Nature 2000)
    span 3 x 25.00 m = 75.00 m
    head 2.60 m

SCOPE OF SERVICES:

  • conceptual designs
  • EIA reports
  • water permit applications
  • feasibility studies
  • applications for financing
  • tender documents for construction works
  • preliminary and detailed designs
  • bills of quantities
  • operation and maintenance manuals for the weirs after reconstruction
  • construction supervision on behalf of the author
  • as-built drawings

Project on map

Project

Weirs on the Oder River

Investor

The State Water Holding Polish Waters - Regional Water Management Authority in Wroclaw

Location

Lower Silesia and Opolskie Voivodships, Poland

Time frame

2009 - 2014